| Work item (summary) | Description (details and purpose) | Priority | Tech/non-tech | PBI created (add number) | Are there dependencies outside TK | Key dependencies (teams or processes) | Planned completion date MM-DY-YR | Status details (latest progress or any notes) | Status (in progress, done) | Lead |
---|
1 | Set-up launch preparation plan in confluence | Create a list of items to complete in preparation for MVP launch both technical software related items, release process related and key operational activities. Be very crisp on the priority of the work so that we are planning for completion of anything that will block MVP launch in production.
| Important | Non-tech | N/A | - | - | 06-04-21 | Populating the plan with what is known already. | Status |
---|
colour | Yellow |
---|
title | In progress |
---|
|
| Sunny |
2 | Ensure that all of the PBI’s and features for MVP launch are captured in Devops | | Important | Tech | N/A | | | 06-28-21 | Started to clean up Devops to have one MVP launch Epic with related features and PBI’s documented. | Status |
---|
colour | Yellow |
---|
title | In progress |
---|
|
| |
3 | Shared learning from recent launches in MSS | | Important | Non-tech | N/A | Yes | MITRACK PO/PM | 06-18-21 | Received some information, compared notes against our draft plans and added anything new. | | Sunny |
4 | Vessel registry high level process documentation | Documentation of business process flow for current state and future state for MVP iteration. This will help for testing of the end to end flow with workload management, and tweak the process so its as smooth as possible for end users.
| Important | Non-tech | N/A | Yes | Registrar supervisors, Change management | 06-14-21 | First part of new process in draft | Status |
---|
colour | Yellow |
---|
title | In progress |
---|
|
| |
5 | Release notes and history documentation | | Important | Non-tech | N/A | - | - | 06-18-21 | Page has been drafted | Status |
---|
colour | Yellow |
---|
title | In progress |
---|
|
| |
6 | Revised registrar work instructions | After the new end to end process flow is ready, the detailed registrar instructions will need to be revised to match new process. In scope will be only the instructions that are impacted by MVP rollout and we will minimize change management activities as much as possible (keeping in same repository and current format etc.). This will help rollout training to the impacted daily users of legacy systems and new workload management. Official SOP required?
| Important | Non-tech | N/A | Yes | Registrars and registrar supervisors | TBD | | | |
7 | Training plan of registrars to use workload management | | Important | Non-tech | N/A | No? | Registrars and registrar supervisors | TBD | | | |
8 | Creation of training artifacts | Creating or modifying the materials, procedures, user guides that already exist to incorporate the new system Updated process documentation to incorporate the new system and modified reality Bi-lingual contents required here?
| | | | | | | | | |
9 | Execution of the training | actually present the training materials and artifacts and post production support materials (SOP’s, tips, guides) bi-lingual training required, through in person or video conference and who does the training
| | | | | | | | | |
10 | MVP rollout strategy and declare target go live date | Figure out the segment of service requests that will be used in the system, including launch timelines and percentage of the population. This will be vital part of the MVP rollout plan as it will allow users to be prepared and additional procedural changes that need to be in place depending on the strategy. We can reduce the change management impacts by keeping engagement of non-impacted users to a minimum during the MVP launch.
| Important | | | | | | | | |
11 | Operational reporting needs | | Critical | Both | | Yes | Business and user team | | | | |
12 | MVP monitoring plan | Figure out the key metrics to track process and system stability and how to track the metrics or needed reporting to support. Without key metrics to track it will be challenging to detect issues and problems and to make sure rollout is having the desired impact.
| Important | Both | - | Yes | Registrar supervisors, BI team | | | | |
13 | Build MVP operational reporting | Create the reporting infrastructure and dashboards that were in the MVP monitoring plan. Ensure that the reporting requirements are collected from the key stakeholders and they have access to the reporting as necessary. | Important | | | | | | | | |
14 | Business approval completed | Send requests for approvals and confirm and document the approvals Examples of the approvals might be TAC, ARB, Authority to operate, sign-off from the business customers etc. Are there other that we are missing? If so, lets confirm and document them in here.
| Critical | | | | | | | | |
15 | Identify User identify management | Who can access the application and putting restrictions in place and what they can do in the application (read, read and write). What different roles are required? (readers, writers and admin). By Anyone in TC that has and within the network with the link would be able to access the application right now.
| Critical | Tech | | Yes | Business and users | | | | |
16 | Modifications to vessel registry forms (pending changes) | | Non-critical | Non-tech | | | | | | | |
17 | Production release process for MVP | | Critical | Both | | | | | | | |
18 | Production release process post-MVP | | Important | Both | | | | | | | |
19 | Issue management process | How feedback and issues will be reported by users and where/how they will be documented Should include the entire process that we use for MVP and beyond Updates needed to the support desk. Communication of the new application and documentation to provide some level of user support
| Important | Both | | | | | | | |
20 | Runbook (MBM) | | Important | Non-tech | | | | | | Status |
---|
colour | Yellow |
---|
title | In progress |
---|
|
| |
21 | UXR strategy | | Important | Non-tech | | | | | | Status |
---|
colour | Yellow |
---|
title | In progress |
---|
|
| |
22 | Execution of UXR strategy | | Important | Non-tech | | | | | | Status |
---|
colour | Yellow |
---|
title | In progress |
---|
|
| |
23 | Review of UXR results and closure of blocking issues | | Important | Non-tech | | | | | | | |
24 | Go no go decision | | Important | Non-tech | N/A | | | | | | |
25 | Communication strategy pre and post launch | How updates on the project will be shared and to whom Do we already have the right forums in place or do we need something special stood up (sprint review is not right forum, maybe we use daily email distribution, confluence page, or blog post on the teams share point, teams channel) Structure of the communication? What key metrics or highlights.
| Important | Non-tech | N/A | | | | | | |
26 | User acceptance testing strategy | | Important | Both | | | | | | | |
27 | Execute post production testing plan | | Important | | | | | | | | |
28 | Provision and deploy to pre-production environments | | Critical | | | Yes | Cloud team? | | | Status |
---|
colour | Yellow |
---|
title | In progress |
---|
|
| |
29 | Provision and deploy to production environments | | Critical | | | Yes | Cloud team? | | | | |
30 | Approvals to launch in production | | Critical | | | Yes | ? | | | | |
31 | | | | | | | | | | | |
32 | | | | | | | | | | | |
33 | | | | | | | | | | | |
34 | New system of record for to house the procedures from the G drive | Training and help documentation is currently in housed in a different repository from workload management. Ideally we can bring the help documentation closer to where the need for it arise, inside vessel registry so its easily accessible during day to day. More thought and options need to be explored for this work. Supports accessibility and easy of updating and keeping documentation fresh and relevant.
| High | Both? | - | Yes | Registrars and registrar supervisors | | | | |
35 | | | | | | | | | | | |