Work item (summary) | Description (details and purpose) | Priority | Tech/non-tech | PBI created (add number) | Are there dependencies outside TK | Key dependencies (teams or processes) | Planned completion date MM-DY-YR | Status details (latest progress or any notes) | Status (in progress, done) | Lead | Notes or open questions | ||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1 | Set-up launch preparation plan in confluence |
| Important | Both | N/A | - | - | 06-04-21 | Populating the plan with what is known already. |
| Sunny | Closed this item once we have a somewhat firm grasp of the remaining work documented on this page. | |||||||
2 | 3 | Ensure that all of the PBI’s and features for MVP launch are captured in Devops |
| Important | Tech | N/A | 06-28-21 | Started to clean up Devops to have one MVP launch Epic with related features and PBI’s documented. |
| Troy | Can close once we feel confident we have remaining PBI’s in the Epic for launch MVP. | ||||||||
43 | Understand application behavior in non-happy path scenarios |
| Important | Tech | ? | Need to discuss this and we close it out once we have a PBI that is completed. | |||||||||||||
54 | Shared learning from recent launches in MSS |
| Important | Non-tech | N/A | Yes | MITRACK PO/PM | 06-18-21 | Received some information, compared notes against our draft plans and added anything new. |
| Sunny | ||||||||
65 | Vessel registry high level process documentation |
| Important | Non-tech | N/A | Yes | Registrar supervisors, Change management | 06-14-21 | First part of new process in draft continue to work on getting it completed. |
| Hugo | ||||||||
76 | Release notes and history documentation |
| Important | Tech | N/A | - | - | 06-30-21 | Page has been drafted need to create a structure and start populating with the key features (tech and user facing) |
| Sunny | Is Confluence or sharepoint a better place for this material? | |||||||
87 | Revised registrar work instructions |
| Important | Non-tech | N/A | Yes | Registrars and registrar supervisors | TBD | We need to define the scope of this work and who is best suited. This is different from training materials? | ||||||||||
98 | Training plan of registrars to use workload management |
| Important | Non-tech | N/A | No? | Registrars and registrar supervisors | TBD | We need a plan to be created that answers:
| ||||||||||
109 | Creation of training artifacts |
| Important | Non-tech | N/A | Yes | -Registrars -Registrar supervisors -Change mgmt | TBD | Should be answered by the training plan. | ||||||||||
1110 | Execution of the training |
| Non-tech | Should be answered by the training plan. | |||||||||||||||
1211 | MVP rollout strategy and declare target go live date |
| Critical | Both | Determine the exact population that will be targetted with MVP.
| ||||||||||||||
1312 | Operational reporting needs |
| Critical | Both | Yes | Business and user team | Need to collect the requirements here for MVP in addition for post MVP. | ||||||||||||
1413 | MVP monitoring plan |
| Important | Both | - | Yes | Registrar supervisors, BI team | Need a discussion about this from a business and IT systems perspective. | |||||||||||
1514 | Operational reporting requirements for MVP |
| Important | Both | Who are the key stakeholders for the purpose of requirements gathering? | ||||||||||||||
1615 | Build MVP operational reporting |
| Important | ? | Depending on the requirements and approach this could combination of tech and non-tech. | ||||||||||||||
1716 | Business approval completed |
| Critical | Non-tech | What are the different approvals that are needed? | ||||||||||||||
1817 | User identify management |
| Critical | Tech | Yes | Business and users | Need the different user roles defined and whom to assign to what roles. | ||||||||||||
1918 | Modifications to vessel registry forms (pending changes) |
| Non-critical | Non-tech | |||||||||||||||
2019 | Production release process for MVP |
| Critical | Both | |||||||||||||||
2120 | Production release process post-MVP |
| Important | Both | |||||||||||||||
2221 | Issue management process |
| Important | Both | |||||||||||||||
2322 | Runbook (MBM) | Important | Tech |
| |||||||||||||||
2423 | UXR strategy | Important | Non-tech |
| |||||||||||||||
2524 | Execution of UXR strategy | Important | Non-tech |
| |||||||||||||||
2625 | Review of UXR results and closure of blocking issues | Important | Non-tech | ||||||||||||||||
2726 | Go no go decision | Important | Both | N/A | |||||||||||||||
2827 | Communication strategy pre and post launch |
| Important | Non-tech | N/A | ||||||||||||||
2928 | User acceptance testing strategy |
| Important | Both | |||||||||||||||
3029 | Execute post production testing plan | Important | Tech | ||||||||||||||||
3130 | Provision and deploy to pre-production environments | Critical | Tech | Yes | Cloud team? |
| |||||||||||||
3231 | Provision and deploy to production environments | Critical | Tech | Yes | Cloud team? | ||||||||||||||
3332 | Approvals to launch in production | Critical | Both | Yes | ? | ||||||||||||||
33 | |||||||||||||||||||
34 | |||||||||||||||||||
35 | |||||||||||||||||||
3637 | New system of record for to house the procedures from the G drive |
| High | Both? | - | Yes | Registrars and registrar supervisors | ||||||||||||
3837 |