Work item (summary) | Description (details and purpose) | Priority (Critical, Important, High) | Work type (Tech, non-tech) | PBI created (number) | Effort/ Complexity Size (L,M,S) | Are there dependencies outside TK | Key dependencies (teams or processes) | Planned completion date MM-DY-YR | Status details (latest progress or any notes) | Status (in progress, done) | Lead | Notes or open questions | |||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1 | Set-up launch preparation plan in confluence |
| Critical | Both | N/A | S | - | - | 06-04-21 | Populating the plan with what is known already. |
| Sunny | Closed this item once we have a somewhat firm grasp of the remaining work documented on this page. | ||||||
2 | MVP rollout strategy and declare target go live date |
| Critical | Both | S | Determine the exact population that will be targeted with MVP.
| |||||||||||||
3 | Business approval completed |
| Critical | Non-tech | M | What are the different approvals that are needed? | |||||||||||||
4 | Operational reporting needs | Come up with the key operational reporting needs for MVP and define how to fulfil the needs. | Critical | Both | M | Yes | Business and user team | Need to collect the requirements here for MVP in addition for post MVP. | |||||||||||
5 | Production release process for MVP | Understand the process that needs to be followed including mandatory approvals to go live in production. | Critical | Both | S | Do we have a documented process that can be followed? If not, we can document the process if we know who can explain this to us. | |||||||||||||
6 | Provision and deploy to pre-production environments | Prepare the DEV, TEST, ACC environments in Azure cloud and push the code into each region without any errors and functioning application. This work will be a precursor for production launch and critical for end users to conduct UAT. | Critical | Tech | M | Yes | Cloud team? TNT? |
| What are the exact regions that are in scope and required? Should we consider TNT in scope here since they are dependency for document management service and vice versa for workload management? | ||||||||||
7 | Provision and deploy to production environments | Prepare the production environment in Azure cloud and push the code in without any errors and functioning application. The application should be accessible to end users and ready for their use. | Critical | Tech | M | Yes | Cloud team? TNT? | Once the application is accessible and ready for use this work items can be closed. Should we consider TNT in scope here since they are dependency for document management service and vice versa for workload management? | |||||||||||
8 | Approvals to launch in production | This is the action of confirming that all of the required approvals have been obtained and that approvals will not be blockers to launching in production. | Critical | Both | ? | Yes | ? | This item is a reminder to make sure we double check that any administrative work is closed out. This is not about understanding what approvals are required as that was a precursor to this work item. | |||||||||||
9 | User identify management |
| Critical | Tech | M | Yes | Business and Vessel registry users, Seafarer users | Need the different user roles defined and whom to assign to what roles. | |||||||||||
10 | Ensure that all of the PBI’s and features for MVP launch are captured in Devops |
| Important | Tech | N/A | S | Yes? | TNT? | 06-28-21 | Started to clean up Devops to have one MVP launch Epic with related features and PBI’s documented. |
| Troy | Can close once we feel confident we have remaining PBI’s in the Epic for launch MVP. | ||||||
11 | Shared learning from recent launches in MSS |
| Important | Non-tech | N/A | S | Yes | MITRACK PO/PM | 06-18-21 | Received some information, compared notes against our draft plans and added anything new. |
| Sunny | We will also work closely with the Seafarer team to share and learn since both teams are trying to launch their MVP around the same time this year. | ||||||
12 | Understand application behavior in non-happy path scenarios |
| Important | Tech | ? | S | Need to discuss this and we close it out once we have a PBI that is completed. | ||||||||||||
13 | Vessel registry high level process documentation |
| Important | Non-tech | N/A | M | Yes | Registrar supervisors, Change management | 06-14-21 | First part of new process in draft continue to work on getting it completed. |
| Hugo | |||||||
14 | Release notes and history documentation |
| Important | Tech | N/A | S | - | - | 06-30-21 | Page has been drafted need to create a structure and start populating with the key features (tech and user facing) |
| Sunny | Is Confluence or sharepoint a better place for this material? | ||||||
15 | Revised registrar work instructions |
| Important | Non-tech | N/A | Yes | Registrars and registrar supervisors | TBD | We need to define the scope of this work and who is best suited. This is different from training materials? | ||||||||||
16 | Training plan of registrars to use workload management |
| Important | Non-tech | N/A | No? | Registrars and registrar supervisors | TBD | We need a plan to be created that answers:
| ||||||||||
17 | Creation of training artifacts |
| Important | Non-tech | N/A | Yes | -Registrars -Registrar supervisors -Change mgmt | TBD | Should be answered by the training plan. | ||||||||||
18 | Execution of the training |
| Important | Non-tech | N/A | Should be answered by the training plan. | |||||||||||||
19 | MVP monitoring plan |
| Important | Both | - | Yes | Registrar supervisors, BI team | Need a discussion about this from a business and IT systems perspective. | |||||||||||
20 | Operational reporting requirements for MVP |
| Important | Both | Who are the key stakeholders for the purpose of requirements gathering? | ||||||||||||||
21 | Build MVP operational reporting |
| Important | ? | Depending on the requirements and approach this could combination of tech and non-tech. | ||||||||||||||
22 | Production release process post-MVP |
| Important | Both | |||||||||||||||
23 | Issue management process |
| Important | Both | |||||||||||||||
24 | Runbook (MBM) | Important | Tech |
| |||||||||||||||
25 | UXR strategy | Important | Non-tech |
| |||||||||||||||
26 | Execution of UXR strategy | Important | Non-tech |
| |||||||||||||||
27 | Summary of UXR results and identification of user blocking issues | Important | Non-tech |
| |||||||||||||||
28 | Closure of UXR issues | Important | Priority of the work item depends on the types of issues. If the issues block the launch then this work is critical, otherwise it is important/high. | ||||||||||||||||
29 | Go no go decision | Important | Both | N/A | |||||||||||||||
30 | Communication strategy pre and post launch |
| Important | Non-tech | N/A | ||||||||||||||
31 | User acceptance testing strategy |
| Important | Both | |||||||||||||||
32 | Execute post production testing plan | Important | Tech | ||||||||||||||||
33 | New system of record for to house the procedures from the G drive |
| High | Both? | - | Yes | Registrars and registrar supervisors | ||||||||||||
34 | Modifications to vessel registry forms (pending changes) |
| Non-critical | Non-tech |
...