Combined Schedule / Process document: RDIMS-18386174-v2-RSIG RELEASE TIMELINE AND PROCESS.DOCX
Note: Below needs to be updated to reflect the attached document
Status | Date | Tasks | Team Members |
---|---|---|---|
6 weeks before release | Sent invite--UAT testing | TL, QA | |
4-6 weeks before release | Testing/Bug Fix | Team | |
4-6 weeks before release | Code Freeze | Team | |
5 weeks before release | Sent Request to Refresh ACC DB and prepare scripts for ACC. | DB | |
5 weeks before release | Create ACC ticket | TL, Team? | |
5 weeks before release | ACC Desk top deployment is ready, package provided to Citrix team | TL, Team? | |
5 weeks before release |
| QA | |
| DB | ||
| |||
|
| ||
4 weeks before release | Send Reminder for UAT Testing. | TL. Please Include the team as well. | |
4 weeks before release | UAT testing | Team, Users, RSIG SD | |
2-3 weeks before release | UAT Signoff | Anne Marie Muldoon (Director, Rail Safety) | |
2 weeks before release |
| TL, Team? | |
| |||
2 weeks before release | Release package for both Desk top and Citrix are provided latest Feb 11th | TL, Team? | |
End | Target release date | Team |