8. Once the Change is created, a Plan tab will be visible. Enter a customized plan for this release. Here is an example from the previous production release:
...
9. Full Text:
Code Block |
---|
Task 1 |
...
– 2023-10-27 RSIG team will place staging files to the staging location under \\ncras22\CSSG Release\CSSG Staging\LEIS\PROD |
...
[C256998] Task 2 – 2023-10-27 RSIG team will notify APPS_WEB team about new staging files have been staged under \\ncras22\CSSG Release\CSSG Staging\LEIS\PROD [C256998] ===================================== |
...
Task 2 -
APPS_WEB / Notify the RSIG team that LEIS PROD is going to be refreshed
Task 3 - 2023-11-01 APPS_WEB / Notify the RSIG team and confirm that LEIS PROD is going to be refreshed on 2023-11-01 (or another day) ===================================== |
...
Task 3 -
APPS_WEB / Stop the LEIS Services and notify the RSIG team
Task 4 - 2023-11-02 9:00 AM APPS_WEB / Stop the LEIS Services and notify the RSIG team ===================================== |
...
Task 4-
Task 5 - 2023-11-02 after 9:00 AM APPS_WEB / Backup existing files for |
...
the: - Two LEIS Business Websites ((Internal Business and External Business) |
...
and - Two LEIS Security Websites ((Internal Security and External Security). |
...
- Four Services (Internal Business, Internal Security, External Business, External Security). |
...
===================================== |
...
Task 5-
Task 6 - 2023-11-02 after 9:00 AM APPS_WEB / Copy the new files from \\ncras22\CSSG Release\WEB Testing\LEIS\PROD [ |
...
to the LEIS PROD servers and website physical folders, install the services.
C256998] to the LEIS PROD servers and website physical folders. Install the services. ===================================== |
...
Task 6-
Task 7 - 2023-11-02 10:00 AM APPS_WEB / Start the LEIS services |
...
APPS_WEB / Notify the RSIG team that LEIS PROD is ready. |
...
===================================== |
...
Task7 -
RSIG/ Perform a sanity check on the LEIS websites
Task 8 - 2023-11-02 RSIG/ Perform a sanity check on the LEIS websites ===================================== |
...
Task 8 -
Task 9 - 2023-11-03 RSIG/ Email all participants (DL OTT Web Monitor Group) to upon completion of the change. |
...
===================================== |
...
Task 9 - |
...
RSIG/Confirmation |
...
of Successful Implementation |
...
By closing this task you are providing proof and confirmation of this Change has been completed & test results have met with expected or acceptable results |
November2023 Deployment
[assembly: AssemblyVersion("1.4.0.0")]
...