Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

  • State is Approved
  • TRIAGE tag is replaced with CODE tag (see Fig. 1 below)
  • Iteration Path is changed to "Marine Safety Portfolio".  Other Ninja Teams may be assigned to work on this CODE ticket: changing the iteration path will make this ticket more easily visible to the other teams.
  • Effort field records any time (in hours) spent determining that this ticket will need a code change to fix.
  • Discussion note added with the following text: "Triage performed by <name>" where <name> is your name.
  • Assigned To field is cleared (unassigned).
  • This bug will now get addressed as part of a future sprint for the system/application named in the Area field. Follow the development and TFS procedures as defined by the SCRUM process and by your scrum master.
  • Ticket in SMGS (see Fig. 2 below) should be closed and a note must be added to the SMGS ticket's Solution text that reads: "Issue being tracked in TFS: <link>.Issue will be fixed in a future release." where <link> will direct client to the triaged TFS ticket.
  • If this bug is preventing clients from using the application/system, procedure to initiate an emergency release should be followed. Contact your team lead/scrum master for further detail.

...

  • State is Committed
  • “FIXED” tag added to the ticket. This tag will help your Scrum Master identify a fix as being completed (in case you are not able to close the related SMGS ticket yourself).
  • Effort (in hours) has been updated to include the time spent fixing the bug.
  • Acceptance criteria includes details of what was fixed and how the fix was applied to the application.
  • A discussion note is added to provide further instruction to your Scrum Master (if needed in special circumstances).

...