Read the page below: How-to migrate Backlog Items from TFS to DevOps
...
Go to TFS and find your project.
...
Click on Work > Queries > New > New Query
...
On Editor, add a filter:
...
Work Item Type
Code Block |
---|
User Story, Bug |
State
Code Block |
---|
To Do,In Progress,Active,New,Pre-Acceptance,User-Acceptance |
...
...
Save query as
...
...
Open a new Excel file, go to Team > New List
...
...
Click on Servers and add 2 servers, one for TFS connection and the other for DevOps connection
...
...
After that, select your TFS Connection > your project > Connect
...
...
In a query list, select your query created before and click on OK
...
...
Now, you can see a list of backlog items in TFS.
...
...
Go to DevOps > Boards > Queries > New query
...
Editor, add a filter:
...
Iteration Path
Code Block |
---|
DSD-CIVAV Support |
Area Path (Use the name of the project being migrated)
Code Block |
---|
DSD-CIVAV Support\NASIMS |
...
Save as
...
Open a new Excel file, go to Team > New List and select your connection with DevOps
...
...
Select your query and click OK
...
Now you can see the list of your backlog items in DevOps
...
...
So, go in your first Excel file with the list of backlog items in TFS and copy all lines
...
Copy all lines in your second Excel file, with the list of backlog items in DevOps
Change User Story to Product Backlog Item
Change the User in Assigned To (if the user doesn’t exist in the list, you can remove the name)
Change Pre-Acceptance or User-Acceptance in State to New
...
Go to TEAM > Publish
...
After this step, each items will have a new ID
...
Return to DevOps and go to Backlog > select DSD-CivAv Support Team and select all new backlog items imported
...
Droit button and Edit
...
Add the Area Path and Save
...
Each new backlog item was like Pre-Acceptance or User-Acceptance in TFS, we need to change the status: New to Commited and Save.
...
If you return in your query in DevOps, you can see all backlog items migrated and with the Area Path correctly.
...
NOTE: You don’t need to create a new query for each project, just change the Area Path in your actual query to the project that will be migrated and Save it.
...