What is an RFC ticket?

Why is it important?

Where to complete the RFC ticket

The RFC ticket is completed in Service Manager.

How to complete

Navigate to tab ‘Change Open Prompt’.

Fill out ‘Change ID’ and ‘Phase’ fields.

Initiator

Fill in fields with details of the team member who will coordinate the release.

Change Detail

Navigate to tab ‘Change Detail’ to the left-hand side of the ‘Change Open Prompt’ tab.

Fill out the following fields:

  • ‘Category’ - Software

  • ‘Impact’ - 4 - User

  • ‘Urgency’ - {2 - High}

  • ‘Risk Assessment’ - {4 - High Risk}

  • ‘Planned Start’ - {prod release start date}

  • ‘Planned End’ - {prod release end date}

Impact / Justification

Navigate to tab ‘Impact / Justification’ to the left-hand side of the ‘Change Open Prompt’ tab.

Fill out the ‘Impact Statement’ field, and include the following details:

  • Number of hours system will be unavailable to users - {30 hours}

  • Indicate why the system will be down - {The system will be down up to 30 hours while the software and databases are updated}

Fill out the ‘Justification’ field, and include the following details:

  • Indicate what will be included in the release - {RSIG production; ROFs / RSIG integration enhancements and bug fixes}

  • Project manager contact - {Project Manager / Contact Rivers, William <william.rivers@tc.gc.ca>}

  • Team lead contact - {Alburger, David <Alburger.David@tc.gc.ca>}

Backout Method

Navigate to tab ‘Backout Method’ to the left-hand side of the ‘Change Open Prompt’ tab.

Fill out the field, and include the following details:

  • Statement indicating that a backout or rollback procedure is in place - {We have a documented roll back procedure for backing out of this change. We will put this document in the deployment folder (RDIMS#: 8964742)

  • Outline rollback procedures -

    • {Microsoft Click Once…}

    • {…}

Plan

Navigate to tab ‘Plan’ to the left-hand side of the ‘Change Open Prompt’ tab.

Fill out the field, and include the following details:

...

{Add tasks - not sure why tasks are listed as the plan, when there is a tab called ‘Tasks’?}

http://smgs.tc.gc.ca/

Ticket Selection

Change Management > Changes > Open New Change

Category > Software

Change Open Prompt

...

Change Detail

...

Impact / Justification

...

Backout Method

...

Plan

...