Release Schedule

Sprint

Due Date

Activity

Team Member(s)

Status

Sprint 32

Wednesday May 31st - Tuesday June 6th

Test all release 1.1.0 tickets in QA environment (general test) and ad-hoc testing

ROF team

Complete

Sprint 32

Tuesday June 6th

Release 1.1.0 active development ends

ROF team

In ProgressComplete

Sprint 32

Tuesday June 6th

Connect RSIG ACC ROF table in ROF

Jugraj

Complete

Sprint 33

Wednesday June 7th - Thursday June 8th

Submit SMGS ticket

Maggie

Complete

Sprint 33

Wednesday June 7th - Friday June 9th

Test all release 1.1.0 tickets in QA environment - general test

ROF team

Not StartedACC testing - frontend

Frontend test v1.1.0

ACC testing - backend

Ewa, Tarek & Jugraj

Complete

Sprint 33

Wednesday June 7th - Wednesday June 14th

UAT testing

UAT v1.1.0

Maggie, UAT testers

Complete

Sprint 33

Wednesday June 14th

QMS and OPS UAT sign-off

Maggie

Complete

Sprint 33

Wednesday June 7th - Tuesday Wednesday June 20th14th

Release 1.1.0 bug fixes (as necessary)

ROF team

Not StartedComplete

Sprint 33

June 13th - 15th

UAT test

ROF users

Not StartedMonday June 19th

See if Ewa and Ashiq are set up in RSIG prod environment for QA testing

Jugraj

Complete

  • Ewa and Ashiq are not in RSIG prod environment

  • RSIG team has completed db tasks

Sprint 33

Friday Monday June 16th

Submit SMGS ticket (needs to be submitted on the Friday before release)

Maggie & Jugraj

Not Started

Sprint 34

Wednesday June 21st

Release 1.1.0 promoted to ACC

Jugraj & Ashiq

Not Started

Sprint 34

Wednesday June 21st - Friday June 23rd

Release 1.1.0 sanity check in ACC

Ewa, Tarek and Maggie

Not Started

Sprint 34

Monday June 26th19th

Day 1 release activities

Jugraj

Complete

Sprint 33

Monday June 19th

Prod staging test

Prod staging test

ROF team; Cary

Complete

Sprint 33

Monday June 19th

Let users know ROF will be unavailable Tuesday morning from approx. 8:00-8:30am

Maggie

Complete

Sprint 33

Tuesday June 20th

Release to prod

Jugraj & Ashiq

Not Started

Sprint

Due Date

Complete

Sprint 33

Tuesday June 20th

Send release notes to users

Maggie

Complete

Day 1 Release Activities - Monday June 19th

Start Time (approx.)

Time to Complete

Activity

Team Member

(s)

Details

Status

TBD

TBD

Submit RSIG SGMS ticket that includes both RSIG and ROF

(Suggested by Andy Labelle on April 14, 2023)

Teams conversation with Andy Labelle:

Every Production Change Request (RFC) is tabled during the Weekly Tuesday Morning CAB (Change Advisory Board) Meeting with all the IT managers and SSC & TC department heads. The goal is to have any RFCs that are targeted for the upcoming change window (Wednesday to Tuesdays) all approved by the proper assignment groups ( IT Security, Database team, Web team, Cooperate Apps team, SSC teams....ect)  So in order for me to get all the approvals in time for the CAB meeting my deadline for you to submit your change is the Friday before that next CAB meeting.... so for example if your target date to do the RSIG change is the 28th then that would fall into the Change window of April 26 to May 2nd. The RFC would be discussed in the April 25th CAB meeting, so your deadline to get a RFC entered (and in the Change planning and assessment phase) would be the Friday of April 21st.

RSIG & ROF team

Not Started

TBD

TBD

Determine if ROFs should be locked when RSIG is locked Friday-Monday for prod release

Not Started

Prod Release Day Activities

Item

Time (approx.)

Effort

1

8:30am

10 min

Assign QA test roles in prod:

  • Jugraj - Manager

  • Maggie - RSI

Jugraj

Complete

2

8:45am

15 min

Merge ACC branch with prod branch

Jugraj

Complete

3

9:00am

20 min

Manually deploy from main branch to prod_staging deployment slot 

Jugraj

Complete

4

9:30am - 11:30am

2 hours

Prod staging test

Cary - test Admin role

Ewa - test Manager role

Maggie - test RSI role

Jugraj - available for troubleshooting

Complete

5

11:30am

10 min

Remove testers from prod roles

Jugraj

Complete

Day 2 Release Activities - Tuesday June 20th

Start Time (approx.)

Time to Complete

Activity

Team Member

Details

Status

When RSIG is locked, ROFs should also be locked and have a blocked message for the users.

1

8:00am

10 min

swap 'prod_staging' deployment slot with 'prod'

Jugraj

Complete

Test Documents