Release Schedule

Sprint

Due Date

Activity

Team Member(s)

Status

Sprint 32

Tuesday June 6th

Release 1.1.0 active development ends

ROF team

In Progress

Sprint 33

Wednesday June 7th

Ensure flags are turned off for non-releasable stories

ROF dev team

Not Started

Sprint 33

Wednesday June 7th - Friday June 9th

Test all release 1.1.0 tickets in QA environment - general test

ROF team

Not Started

Sprint 33

Wednesday June 7th - Tuesday June 20th

Release 1.1.0 bug fixes (as necessary)

ROF team

Not Started

Sprint 33

June 13th - 15th

UAT test

ROF users

Not Started

Sprint 33

Friday June 16th

Submit SMGS ticket (needs to be submitted on the Friday before release)

Maggie & Jugraj

Not Started

Sprint 34

Wednesday June 21st

Release 1.1.0 promoted to ACC

Jugraj & Ashiq

Not Started

Sprint 34

Wednesday June 21st - Friday June 23rd

Release 1.1.0 sanity check in ACC

Ewa, Tarek and Maggie

Not Started

Sprint 34

Monday June 26th

Release to prod

Jugraj & Ashiq

Not Started

Prod Release Day Activities

Item

Time (approx.)

Effort

Activity

Team Member

Details

Status

When RSIG is locked, ROFs should also be locked and have a blocked message for the users.