5Sprint | Due Date | Activity | Team Member(s) | Status |
---|---|---|---|---|
Sprint 36 | Tuesday July 4th | Release 1.2.0 active development ends | ROF team | Not Started |
Sprint 35 | Wednesday July 5th - Thursday July 7th | Submit SMGS ticket | Maggie | Not Started |
Sprint 35 | Wednesday July 5th - Friday July 7th | ACC testing - frontend ACC testing - backend | Ewa, Tarek & Jugraj | Not Started |
Sprint 35 | Wednesday July 5th - Friday July 7th | UAT testing | Maggie, UAT testers | Not Started |
Sprint 35 | Wednesday July 5th - Wednesday July 12th | Release 1.2.0 bug fixes (as necessary) | ROF team | Not Started |
Sprint 33 | Thursday July 13th | Prod staging test | ROF team; Cary | Not Started |
Sprint 33 | Friday July 14th | Release to prod | Jugraj | Not Started |
Day 1 Release Activities - Thursday July 13th
Start Time (approx.) | Time to Complete | Activity | Team Member | Details | Status | |
---|---|---|---|---|---|---|
1 | 8:30am | 10 min | Assign QA test roles in prod:
| Jugraj | Not Started | |
2 | 8:45am | 15 min | Merge ACC branch with prod branch | Jugraj | Not Started | |
3 | 9:00am | 20 min | Manually deploy from main branch to prod_staging deployment slot | Jugraj | Not Started | |
4 | 9:30am - 11:30am | 2 hours | Prod staging test | Cary - test Admin role Ewa - test Manager role Maggie - test RSI role Jugraj - available for troubleshooting |
| Not Started |
5 | 11:30am | 10 min | Remove testers from prod roles | Jugraj | Not Started |
Day 2 Release Activities - Friday July 14th
Start Time (approx.) | Time to Complete | Activity | Team Member | Details | Status | |
---|---|---|---|---|---|---|
1 | 8:00am | 10 min | swap 'prod_staging' deployment slot with 'prod' | Jugraj | Not Started |
Test Documents
Title | Document |
---|---|
UAT | |
ACC | |
Prod staging |