Skip to end of metadata
Go to start of metadata

You are viewing an old version of this page. View the current version.

Compare with Current View Page History

« Previous Version 43 Next »

Return to MAACE Project Gating Status main page MAACE Project Gating Status

Phase 1 (Concept Case / Gate 1 proposal deck)

Phase 2 (Business Case / Gate 2 proposal desk)

Phase 3: Project Charter / PMP, Stakeholder, Change & Communication Management Plans

Phase 4 (Project Dashboard / Gate 4 proposal deck)

Phase 5 - Close Out Memo / Close out report

Manager: Justin Green

RDIMS Project Folder: #16465422)

Vessel Registry Project SharePoint Folder Link

  • Concept Case (RDIMS # 16072004)
  • Gate 1 Proposal Deck (RDIMS # 16200444)
  • Project Control Sheet (RDIMS # 16715491)
  • Project Dashboard (RDIMS # 15925115)
  • Project Spending Plan (RDIMS # 15923040)
  • Rasci Matrix 1 (RDIMS ??)
  • Stakeholder Management Plan (RDIMS # 17318356)
  • Change Management Plan (incl. Communications Plan) (RDIMS # 17318425)
  • Project Benefit Realization Plan (RDIMS # 17686486)
  • Risk & Issue Log (RDIMS # 16708591)
  • Project Lessons Learned Log (RDIMS # 16754728)
  • Project Change Request Log (RDIMS # 17684019 )
  • FMA Review
  • ARB (Jan 14, 2020, date TBC)
  • EOC (Jan 21, 2020 date TBC)
  • DGH (Jan 24, 2020 date TBC))
  • RMC (Mar 8, 2020 date TBC))
  • ADM-IM (date TBC))
  • Gate 1 Approved - (Date TBC)
  • Project Classification Assessment & Resource Demand Forecast Tool (Justification of Risk and Profile Levels) (RDIMS # 16758079)
  • EA Options Analysis
  • PMF Financial Table (RDIM # 17073050)
  • SA&A Level of Assurance
  • SA&A Level - Statement of Sensitivity
  • Business Case (RDIMS # 17134135)
  • Gate 2 Proposal Deck (RDIMS # 16633607)
  • TAC Deck for recommendation (RDIMS # 17289924)
  • ARB approval Deck (RDIMS # 16718986)
  • IMB Deck (depending of Risk Profile) (RDIMS # 17383267)
  • FMA Review (Date TBC)
  • EOC (Oct 6, 2020)
  • DGH (Date TBC)
  • ADM-IM (Jan 15, 2021)
  • IMB Approval (Apr 15, 2021) (RDIMS # 17449431)
  • Gate 2 Approved - April 15, 2021 (RDIMS # 17449431)
  • Start of Phase 3 (April 16, 2021)
  • Project Charter - PMP Deck (RDIMS # 17223599)
  • Project Management Plan (RDIMS # 17223577)
  • Change Management Plan (incl. Communication Plan (RDIMS # 17318425)
  • Stakeholder Management Plan (RDIMS # 17318356)
  • TAC Report (RDIMS # 17552772 )
  • TAC Recommendation (RDIMS# 17552772 (Date May 17, 2021)
  • TAC Deck for recommendation (RDIMS # 17289924 )
  • ARB Endorsement (June 14, 2021)
  • FMA Approval ( requested by May 14, 2021)
  • EOC Endorsement (meeting approved on May 27, 2021)
  • Signed Project Charter (RDIMS # 17665054 )
  • ADM-IM Endorsement (July 15, 2021 (RDIMS # 15797681)
  • IMB Gate 3 Deck (RDIMS # 17686480 )
  • IMB Approval (Aug 18, 2021) (RDIMS # 17836376)
  • Gate 3 sign-off (Aug 18, 2021)
  • Start of Phase 5 (April 30, 2022)
  • SRTM - Security Requirements Traceability Matrix Level of Assurance (LoA) Document (RDIMS # 16584975Security Testing Results
  • Test Plan & Results (included in each Dev Ops Sprint prior to any releases Team Kraken Backlog items Backlog - Boards (azure.com))
  • ATO - Authority to Operate
  • Review & Update Benefit Realization Plan (RDIMS # 17686486)
  • Finalized Lessons Learned Log (RDIMS # 16754728)
  • Finalized PMF Project Dashboard (RDIMS # 15925115)
  • PMF Gate 5 Close Out Report Deck  (RDIMS # 18593606)
  • FMA Review
  • EOC (June 28, 2022)
  • ARB (June 27, 2022)
  • ADM-IM (June 30, 2022)
  • IMB (Date Here)
  • Gate 5 Sign-Off (Date Here
  • No labels