Table of Contents | ||||
---|---|---|---|---|
|
...
5Sprint | Due Date | Activity | Team Member(s) | Status |
---|---|---|---|---|
Sprint 38 | Tuesday August 29th | Release 1.4.0 active development ends | ROF team | Not Started |
Sprint 39 | Wednesday August 30th- Thursday August 31st | Submit SMGS ticket | Maggie | Not Started |
Sprint 39 | Wednesday August 30th - Friday September 1st | ACC testing - frontend ACC testing - backend | Ewa, Tarek & Jugraj | Not Started |
Sprint 39 | Monday September 4th | Labour Day | ROF team | Holiday |
Sprint 39 | Wednesday August 30th - Tuesday September 5th | UAT testing | Maggie, UAT testers | Not Started |
Sprint 39 | Wednesday August 30th - Wednesday September 6th | Release 1.4.0 bug fixes (as necessary) | ROF team | Not Started |
Sprint 39 | Thursday September 7th | Prod staging test | ROF team; Cary | Not Started |
Sprint 39 | Friday September 8th | Release to prod | Jugraj | Not Started |
Day 1 Release Activities - Thursday September 7th
Start Time (approx.) | Time to Complete | Activity | Team Member | Details | Status | |
---|---|---|---|---|---|---|
1 | 8:30am | 10 min | Assign QA test roles in prod:
| Jugraj | Not Started | |
2 | 8:45am | 15 min | Merge ACC branch with prod branch | Jugraj | Not Started | |
3 | 9:00am | 20 min | Manually deploy from main branch to prod_staging deployment slotĀ | Jugraj | Not Started | |
4 | 9:30am - 11:30am | 2 hours | Prod staging test | Cary - test Admin role Ewa - test Manager role Maggie - test RSI role Jugraj - available for troubleshooting |
| Not Started |
5 | 11:30am | 10 min | Remove testers from prod roles | Jugraj | Not Started |
Day 2 Release Activities - Friday September 8th
Start Time (approx.) | Time to Complete | Activity | Team Member | Details | Status | |
---|---|---|---|---|---|---|
1 | 8:00am | 10 min | swap 'prod_staging' deployment slot with 'prod' | Jugraj | Not Started |
Test Documents
Title | Document |
---|---|
UAT | |
ACC | |
Prod staging |
...