5Sprint

Due Date

Activity

Team Member(s)

Status

Sprint 38

Tuesday August 29th

Release 1.4.0 active development ends

ROF team

Not Started

Sprint 39

Wednesday August 30th- Thursday August 31st

Submit SMGS ticket

Maggie

Not Started

Sprint 39

Wednesday August 30th - Friday September 1st

ACC testing - frontend

Frontend test v1.1.0

ACC testing - backend

Ewa, Tarek & Jugraj

Not Started

Sprint 39

Monday September 4th

Labour Day

ROF team

Holiday

Sprint 39

Wednesday August 30th - Tuesday September 5th

UAT testing

UAT v1.1.0

Maggie, UAT testers

Not Started

Sprint 39

Wednesday August 30th - Wednesday September 6th

Release 1.4.0 bug fixes (as necessary)

ROF team

Not Started

Sprint 39

Thursday September 7th

Prod staging test

Prod staging test

ROF team; Cary

Not Started

Sprint 39

Friday September 8th

Release to prod

Jugraj

Not Started

Day 1 Release Activities - Thursday September 7th

Start Time (approx.)

Time to Complete

Activity

Team Member

Details

Status

1

8:30am

10 min

Assign QA test roles in prod:

  • Ewa - Manager

  • Maggie - RSI

Jugraj

Not Started

2

8:45am

15 min

Merge ACC branch with prod branch

Jugraj

Not Started

3

9:00am

20 min

Manually deploy from main branch to prod_staging deployment slot 

Jugraj

Not Started

4

9:30am - 11:30am

2 hours

Prod staging test

Cary - test Admin role

Ewa - test Manager role

Maggie - test RSI role

Jugraj - available for troubleshooting

Not Started

5

11:30am

10 min

Remove testers from prod roles

Jugraj

Not Started

Day 2 Release Activities - Friday September 8th

Start Time (approx.)

Time to Complete

Activity

Team Member

Details

Status

1

8:00am

10 min

swap 'prod_staging' deployment slot with 'prod'

Jugraj

Not Started