Release 1.1.0 - Tuesday June 20th, 2023

Date

Activity

Tasks

Team

Thursday June 15th

QMS: Workshop to complete UAT

  1. Complete QMS UAT testing

Thursday June 15th

UAT: QMS sign-off

  1. Confirm UAT is complete to RSIG business satisfaction, and we can release on Tuesday June 20th

RSIG business / QMS team

Thursday June 15th

UAT: OPS sign-off

  1. Complete OPS UAT testing

  2. Optional: OPS team can provide opinion as to whether or not enough OPS testing has been complete

OPS

Thursday June 15th

Email OPS users regarding ROF down-time due to release

  1. OPS users informed ROF will be offline between 8:00-8:30am (approx.) via email

ROF

Note: ROF team currently has an email, but RSIG business may want to take over in the future?

Tuesday June 19th

ROF release to prod

  1. ROF team release to prod

ROF

Tuesday June 19th

Email OPS users release notes

  1. OPS users sent release notes via email

ROF

Note: ROF team currently has an email, but RSIG business may want to take over in the future?

Release 1.2.0 Friday July 14th, 2023

Date

Activity

Tasks

Team

UAT: QMS sign-off

  1. Complete QMS UAT testing

  2. Confirm UAT is complete to RSIG business satisfaction, and we can release on Tuesday June 20th

RSIG business / QMS team

Thursday June 15th

UAT: OPS sign-off

  1. Complete OPS UAT testing

  2. Optional: OPS team can provide opinion as to whether or not enough OPS testing has been complete

OPS

Thursday June 15th

  1. OPS users informed ROF will be offline between 8:00-8:30am (approx.)

ROF

Tuesday June 19th

ROF release to prod

  1. ROF team release to prod

ROF

Release Schedule

Sprint

Due Date

Activity

Team Member(s)

Status

Sprint 32

Wednesday May 31st - Tuesday June 6th

Test all release 1.1.0 tickets in QA environment (general test) and ad-hoc testing

ROF team

Complete

Sprint 32

Tuesday June 6th

Release 1.1.0 active development ends

ROF team

Complete

Sprint 32

Tuesday June 6th

Connect RSIG ACC ROF table in ROF

Jugraj

Complete

Sprint 33

Wednesday June 7th - Thursday June 8th

Submit SMGS ticket

Maggie

Complete

Sprint 33

Wednesday June 7th - Friday June 9th

ACC testing - frontend

Frontend test v1.1.0

ACC testing - backend

Ewa, Tarek & Jugraj

Complete

Sprint 33

Wednesday June 7th - Wednesday June 14th

UAT testing

UAT v1.1.0

Maggie, UAT testers

In Progress

Sprint 33

Wednesday June 14th

QMS and OPS UAT sign-off

Maggie

In Progress

Sprint 33

Wednesday June 7th - Wednesday June 14th

Release 1.1.0 bug fixes (as necessary)

ROF team

In Progress

Sprint 33

Thursday June 15th

Let users know ROF will be unavailable Tuesday morning from approx. 8:00-8:30am

Maggie

Not Started

Sprint 33

Monday June 19th

Prod staging test

Prod staging test

ROF team; Cary

Not Started

Sprint 33

Tuesday June 20th

Release to prod

Jugraj

Not Started

Sprint 33

Tuesday June 20th

Send release notes to users

Maggie

Not Started

Day 1 Release Activities - Monday June 19th

Start Time (approx.)

Time to Complete

Activity

Team Member

Details

Status

1

8:30am

10 min

Assign QA test roles in prod:

  • Ewa - Manager

  • Maggie - RSI

Jugraj

Not Started

2

8:45am

15 min

Merge ACC branch with prod branch

Jugraj

Not Started

3

9:00am

20 min

Manually deploy from main branch to prod_staging deployment slot 

Jugraj

Not Started

4

9:30am - 11:30am

2 hours

Prod staging test

Cary - test Admin role

Ewa - test Manager role

Maggie - test RSI role

Jugraj - available for troubleshooting

Not Started

5

11:30am

10 min

Remove testers from prod roles

Jugraj

Not Started

Day 2 Release Activities - Tuesday June 20th

Start Time (approx.)

Time to Complete

Activity

Team Member

Details

Status

1

8:00am

10 min

swap 'prod_staging' deployment slot with 'prod'

Jugraj

Not Started