Release v1.1.0 & v1.2.0 Schedule
Release 1.1.0 - Tuesday June 20th, 2023
Date | Activity | Tasks | Team |
---|---|---|---|
Thursday June 15th | QMS: Workshop to complete UAT |
| QMS & ROF |
Thursday June 15th | UAT: QMS sign-off |
| RSIG business or QMS & ROF |
Thursday June 15th | UAT: OPS sign-off |
| OPS & ROF |
Thursday June 15th | Email OPS users regarding ROF down-time due to release |
| ROF Note: ROF team currently has an email, but QMS may want to take over in the future? |
Monday June 19th | Prod Staging: OPS to test Admin role |
| OPS & ROF |
Tuesday June 20th | ROF release to prod |
| ROF |
Tuesday June 20th | Email OPS users release notes |
| ROF Note: ROF team currently has an email, but QMS may want to take over in the future? |
Release 1.2.0 Friday July 14th, 2023
Date | Activity | Tasks | Team |
---|---|---|---|
Thursday June 29th | QMS ROF training |
| ROF & QMS |
Wednesday July 5th - Friday July 7th | UAT: QMS |
| QMS & ROF |
Wednesday July 5th - Friday July 7th | UAT: OPS |
| OPS & ROF |
Monday July 10th | UAT: QMS sign-off |
| RSIG business or QMS & ROF |
Wednesday July 12th | Email OPS users regarding ROF down-time due to release |
| ROF or QMS |
Thursday July 13th | Prod Staging: OPS to test Admin role |
| OPS & ROF |
Friday July 14th | ROF release to prod |
| ROF |
Friday July 14th | Email OPS users release notes |
| ROF or QMS |
ROF UAT: Required # of users
Group | # of Users |
---|---|
QMS | One |
OPS | Two |
ROF UAT: Testing breakdown
Option | UAT testing tasks |
---|---|
Option #1 | All three testers test entire UAT spreadsheet. All features will be tested 3x. |
Option #2 | UAT testing split the UAT spreadsheet, and 1/3 of features listed. All features will be tested 1x. |
Option #3 | Other?? |