Release Schedule
Sprint | Due Date | Activity | Team Member(s) | Status |
---|---|---|---|---|
Sprint 32 | Friday June 2nd | Ensure flags are turned off for non-releasable stories | ||
Sprint 32 | Tuesday June 6th | Release 1.1.0 active development ends. Deploy to QA and ACC. | ROF team | In Progress |
Sprint 33 | Wednesday June 7th - Friday June 9th | Test all release 1.1.0 tickets in QA environment - general test | ROF team | Not Started |
Sprint 33 | Wednesday June 7th - Tuesday June 20th | Release 1.1.0 bug fixes (as necessary) | ROF team | Not Started |
Sprint 33 | June 13th - 15th | UAT test in QA | ROF users | Not Started |
Sprint 33 | Friday June 16th | Submit SMGS ticket (needs to be submitted on the Friday before release) | Maggie & Jugraj | Not Started |
Sprint 33 | Wednesday June 21st - Friday June 23rd | Release 1.1.0 frontend QA testing | Ewa, Tarek and Maggie | Not Started |
Sprint 34 | Wednesday June 21st - Friday June 23rd | Release 1.1.0 dev ad-hoc testing in QA | Jugraj & Ashiq | Not Started |
Sprint 34 | Monday June 26th | Prod staging smoke check | Ewa, Jugraj and Maggie (and Cary - he could map a location) | Not Started |
Sprint 34 | Tuesday June 27th | Release to prod | Jugraj & Ashiq | Not Started |
Prod Release Day Activities
Start Time (approx.) | Time to Complete | Activity | Team Member | Details | Status | |
---|---|---|---|---|---|---|
1 | 9:00am | 10 min | Switch connection string from training to prod | Jugraj | Not Started | |
2 | 10:00am | 15 min | Assign QA test roles in prod:
| Jugraj | Not Started | |
3 | 10:30am | 15 min | Re-upload document templates to SCED prod environment | Jugraj |
| N/A? |
4 | 11:00am or earlier (confirm with RSIG) | 20 min | Merge ACC branch with main branch | Jugraj | Not Started | |
5 | 11:30am | 20 min | Manually deploy from main branch to prod app service | Jugraj | Not Started | |
6 | 1:00pm - 3:00pm | 2 hours | Step 3: Prod Sanity Check on release day | Grace - test Admin role Ashiq - test Manager role -test RSI role Jugraj - available for troubleshooting | Can we skip if test in prod staging? | |
7 | 3:00pm | 15 min | Step 4: Remove Grace and Maggie from prod environment. Jugraj can remain in prod environment as Admin. | Jugraj | Can we skip if test in prod staging? | |
8 |