Seafarer Credentials - CD06 - Project Gating Status

Return to MAACE Project Gating Status main page MAACE Product Management / Project Gating Status

Phase 1 (Concept Case / Gate 1 proposal deck)

Phase 2 (Business Case / Gate 2 proposal desk)

Phase 3: Project Charter / PMP, Stakeholder, Change & Communication Management Plans

Phase 4 (Project Dashboard / Gate 4 proposal deck)

Phase 5 (Close out memo / Close out report)

Phase 1 (Concept Case / Gate 1 proposal deck)

Phase 2 (Business Case / Gate 2 proposal desk)

Phase 3: Project Charter / PMP, Stakeholder, Change & Communication Management Plans

Phase 4 (Project Dashboard / Gate 4 proposal deck)

Phase 5 (Close out memo / Close out report)

Manager: Justin Green

RDIMS Project Folder #: 17239760

RDIMS Document Reference For CD03, CD04, CD06 - Asset Creation Forms For Processing

 

Seafarer Credential Project SharePoint Folder link

Concept Case (RDIMS # 15715008)
Gate 1 Proposal Deck (Feb 13, 2020) (RDIMS # 16060372)
Project Control Sheet (RDIMS # 16873534)
Project Dashboard (RDIMS # 15925155)
Project Spending Plan (RDIMS # 15924707)
Rasci Matrix
Change Management Plan (incl. Communication Plan (RDIMS # 17397384)
Stakeholder Management Plan (RDIMS # 17433313)
Project Benefit Realization Plan (RDIMS #17686447)
Risk & Issue Log (RDIMS # 16876986)
Project Lessons Learned Log (RDIMS #16876803)
Change Request Log RDIMS # 17686288
FMA Review
EOC (Date TBC)
DGH (Date TBC)
ADM-IM (Feb 13, 2020)
IMC (Date TBC)
Gate 1 Approved - Date required
Project Classification Assessment & Resource Demand Forecast Tool (Justification of Risk and Profile Levels) (RDIMS #17378434)
EA Options Analysis
SA&A Level of Assurance
SA&A Level - Statement of Sensitivity
Business Case (RDIMS #16877005)
Signed Business Case (March 25, 2021) (RDIMS # 17132681)
Gate 2 Proposal Deck (Jan 29, 2021) (RDIMS # 16876997)
IMB Deck (RDIMS # 17383274)
FMA Review (Date TBC)
EOC (Oct 6, 2020)
DGH (Date TBC)
ADM-IM (Mar 4, 2021)
IMB Approval (Apr 15, 2021) (RDIMS #17449431)
Gate 2 Approved - April 15, 2021
Start of Phase 3 (April 16, 2021)
TAC Deck for recommendation (RDIMS # 17312207)
ARB approval Deck (RDIMS # 17217752)
Project Charter - PMP Deck (RDIMS #17149887)
Project Charter - Final Signed PDF version approved on June 23, 2021 (RDIMS #17663780)
Project Management Plan (RDIMS #17397413)
Change Management Plan (incl. Communication Plan (RDIMS # 17397384)
Stakeholder Management Plan (RDIMS # 17433313)
FMA Review (by May 7, 2021)
TAC Report (RDIMS # 17312207)
TAC Recommendation (May 17, 2021)
TAC Deck for recommendation (RDIMS # 17217752 )
ARB Endorsement (June 14, 2021)
EOC (meeting approved on May 27, 2021)
Signed Project Charter (RDIMS # 17663780 )
ADM-IM (July 15, 2021) (RDIMS # 15797681)
IMB Deck (RDIMS# 17686427)
IMB Approval (Aug 18, 2021) (RDIMS # 17836376)
Gate 3 sign-off (Aug 18, 2021)
Start of Phase 5 (March 31, 2022)
SRTM - Security Requirements Traceability Matrix Level of Assurance (LoA) Document (RDIMS # 17242719 & 17558453 )
iATO - Authority to Operate (RDIMS # 18752207
Review & Update Benefit Realization Plan (RDIMS #17686447)
Finalized Lessons Learned Log (RDIMS #16876803)
Finalized PMF Project Dashboard (RDIMS # 15925155)
PMF Gate 5 Close Out Report Deck ( RDIMS # 18593505)
PMF Gate 5 Close Out Report Deck PDF signed copy ( RDIMS # 18705683)
FMA Review (June 16, 2022)
EOC (June 28, 2022)RDIMS # 18724323)
ADM-IM (July 14, 2022, Gate 5 Presentation signed by ADM and CDO July 25, 2022)
DG-IM (Sept 30, 2022) RDIMS # 18984956 (email from EPMO confirming RDIMS #19047404
IMB (Date Here)
Gate 5 Sign-Off (Date Here