Return to MAACE Project Gating Status main page MAACE Project Gating Status

Phase 1 (Concept Case / Gate 1 proposal deck)

Phase 2 (Business Case / Gate 2 proposal desk)

Phase 3: Project Charter / PMP, Stakeholder, Change & Communication Management Plans

Phase 4 (Project Dashboard / Gate 4 proposal deck)

Phase 5 (Close out memo / Close out report)

Manager: Justin Green

RDIMS Project Folder #: 17239760

Seafarer Credential Project SharePoint Folder link

  • Concept Case (RDIMS # 15715008)
  • Gate 1 Proposal Deck (Feb 13, 2020) (RDIMS # 16060372)
  • Project Control Sheet (RDIMS # 16873534)
  • Project Dashboard (RDIMS # 15925155)
  • Project Spending Plan (RDIMS # 15924707)
  • Rasci Matrix
  • Change Management Plan (incl. Communication Plan (RDIMS # 17397384)
  • Stakeholder Management Plan (RDIMS # 17433313)
  • Project Benefit Realization Plan (RDIMS #17686447)
  • Risk & Issue Log (RDIMS # 16876986)
  • Project Lessons Learned Log (RDIMS #16876803)
  • Change Request Log RDIMS # 17686288
  • FMA Review
  • EOC (Date TBC)
  • DGH (Date TBC)
  • ADM-IM (Feb 13, 2020)
  • IMC (Date TBC)
  • Gate 1 Approved - Date required
  • Project Classification Assessment & Resource Demand Forecast Tool (Justification of Risk and Profile Levels) (RDIMS #17378434)
  • EA Options Analysis
  • SA&A Level of Assurance
  • SA&A Level - Statement of Sensitivity
  • Business Case (RDIMS #16877005)
  • Signed Business Case (March 25, 2021) (RDIMS # 17132681)
  • Gate 2 Proposal Deck (Jan 29, 2021) (RDIMS # 16876997)
  • IMB Deck (RDIMS # 17383274)
  • FMA Review (Date TBC)
  • EOC (Oct 6, 2020)
  • DGH (Date TBC)
  • ADM-IM (Mar 4, 2021)
  • IMB Approval (Apr 15, 2021) (RDIMS #17449431)
  • Gate 2 Approved - April 15, 2021
  • Start of Phase 3 (April 16, 2021)
  • TAC Deck for recommendation (RDIMS # 17312207)
  • ARB approval Deck (RDIMS # 17217752)
  • Project Charter - PMP Deck (RDIMS #17149887)
  • Project Charter - Final Signed PDF version approved on June 23, 2021 (RDIMS #17663780)
  • Project Management Plan (RDIMS #17397413)
  • Change Management Plan (incl. Communication Plan (RDIMS # 17397384)
  • Stakeholder Management Plan (RDIMS # 17433313)
  • FMA Review (by May 7, 2021)
  • TAC Report (RDIMS # 17312207)
  • TAC Recommendation (May 17, 2021)
  • TAC Deck for recommendation (RDIMS # 17217752 )
  • ARB Endorsement (June 14, 2021)
  • EOC (meeting approved on May 27, 2021)
  • Signed Project Charter (RDIMS # 17663780 )
  • ADM-IM (July 15, 2021) (RDIMS # 15797681)
  • IMB Deck (RDIMS# 17686427)
  • IMB Approval (Aug 18, 2021) (RDIMS # 17836376)
  • Gate 3 sign-off (Aug 18, 2021)
  • Start of Phase 5 (March 31, 2022)
  • SRTM - Security Requirements Traceability Matrix Level of Assurance (LoA) Document (RDIMS # 17242719 & 17558453 )
  • Test Plan & Result Document (DSD - Marine Certification - Seafarer Credentials Project Stats -  DevOps)
  • ATO - Authority to Operate (RDIMS # 18534719
  • Review & Update Benefit Realization Plan (RDIMS #17686447)
  • Finalized Lessons Learned Log (RDIMS #16876803)
  • Finalized PMF Project Dashboard (RDIMS # 15925155)
  • PMF Gate 5 Close Out Report Deck ( RDIMS # 18593505)
  • PMF Gate 5 Close Out Report Deck PDF signed copy ( RDIMS # 18705683)
  • FMA Review (June 16, 2022)
  • EOC (June 28, 2022)
  • ADM-IM (July 7, 2022)
  • DG-IM (Date Here)
  • IMB (Date Here)
  • Gate 5 Sign-Off (Date Here
  •  