RSIG Release 35 schedule - April 2023

Status 

Date 

Tasks 

Team Members 

Complete 

March 3rd 

Request Data Management approval for DB changes (approve data model changes (if any) 

Once approved, CC to Data Warehouse group (André Roy) with the latest approved model. (Done on April 27th this time. should be earlier)

Xu –  

Done. Submitted March 3rd, Approved March 6th

Complete 

March 16th 

Send Invite for UAT Testing 

Annick – Done March 16th. Reminders sent since.  

 In progress

 March 24th - April 6th

Feature Freeze, Testing/Bug Fixes & Regression Testing 

Honglei, Ewa, RSIG Team

Complete 

March 13th 

Sent Request to Refresh ACC DB and prepare scripts for ACC. 

Xu – done  

Complete

April 27th

Send email to Data Warehouse group (André Roy) for schema change for RSIG release and RSIG_ACC is ready for their ETL job testing.

 

Inform them the PROD release date if applicable.

Xu - done but should be earlier notice next time.

Complete 

March 15th 

Prepare for UAT Testing 

Honglei – Done 

Complete 

March 15th 

Create ACC ticket 

Entai – Done 

Complete 

March 23rd 

ACC Desktop deployment is ready, package provided to Citrix Team 

Entai – Done  

Complete 

March 29th 

Determine UAT sign-off criteria.

Allison, Ann Marie, Steve, Annick 

 Complete

March 27th – 29th 

Testing of ACC build – citrix & desktop 

 Completed by Honglei March 29th

 Complete

Started March 21st 

 

To be done by Wednesday April 12th 

UAT testing / Regression Testing

Honglei – in progress 

RSIG Users have conducted some regression testing as of March 29th.

Rest of RSIG team is performing regression testing. 

Holiday

April 7-10 Easter long weekend

 

 

 Complete

Wednesday April 12th 

UAT Sign-off (historically 2-3 weeks before release) 

Anne Marie, Allison, Steve 

 Complete

Wednesday April 12th 

Code Freeze 

Honglei closes the ticket under the ACC ticket. C255827

 Complete

Friday April 14th 

Change Management Activities 

Entai – SMGS ticket for production release has been prepared in advance on March 27th.  

Dave to submit when we are ready to do so. Deadline is Friday April 14th.

C255883

 Complete

Friday April 14th 

Release package for both Desktop and Citrix are provided 

George 

Annick isn’t available, this won’t be done.

Monday April 17th -

Due By Thursday April 20th 

 

Create user-friendly release notes 

Annick 

 

Monday April 17th -Thursday April 20th 

Find two “smoke testers” to test the production environment on the day of release.

Annick 

 

Tuesday April 25th 

 

Advise users that RSIG will be offline from April 28th – to morning of May 1st 

Annick 

 Complete

Tuesday April 25th 

Update RSIG start-up message 

Shu Zi 

 

Wednesday April 26th 

Send Shu Zi “smoke tester” names.

Annick 

 

Friday April 28th 

 

Release Day - Coordinate “Smoke Test” (Desktop) 

Honglei 

 

Friday April 28th 

 

Release Day - Help Desk sends out release notes to users.

Annick 

 

Friday April 28th 

Release Day (Desktop and Citrix) - Coordinate with database group.

Xu 

 Complete

Friday April 28th 

Release Day (Desktop and Citrix) - Coordinate deployment 

note: work with server group to ensure accuracy (shared Services)

George 

 

Saturday April 29th 

Release Day (Citrix) - Test Citrix and release when ready 

Honglei, Xu 

 

Monday May 1st 

Let users know they can install the updated version of RSIG and ensure they have the correct version.

Annick 

 

Monday May 1st

Done

Finished

 

 

Release Day Activities

2-3 days prior to Release

Item

Status

Time (Estimate ONLY)

What to Do

Team

Item

Status

Time (Estimate ONLY)

What to Do

Team

00

Complete

 

Contact DBA team to make sure whoever run script on release day has account in TC008.

Xu

Release Day (April 28th, 2023) (Friday)

Item

Status

Time (Estimate ONLY)

What to Do

Team

Item

Status

Time (Estimate ONLY)

What to Do

Team

1

Complete

7:00am-7:30am

Lock PROD

Xu

2

Complete

7:00am-7:30am

Confirm regular user cannot launch RSIG.

RSIG QA (Honglei)

3

Complete

7:00am-7:30am

Let DBA Know that can start Release process

Xu

4

Complete

7:30am

Back Up PROD and run scripts. Once done, please let Xu Know.

TC DBA (Andree)

5

Complete

8:00

Deploy updated TSB SSIS to PROD and let Xu know.

TC DBA (Andree)

6

Complete

8:10

Validate SSIS package ad hoc run

Xu

7

Complete

8:20

Schedule SSSI daily run at 5am.

TC DBA (Andree)

8

Complete

8:40am

Verify PROD DB for DB setting, schema compare, Release message, version attribute set up, permissions, etc.

Xu

9

Complete

8:40am

Verify PROD DB for Data Update

Xu and Shuzi

10

Complete

9:00am

Let George know when PROD DB is ready

Xu

11

Complete

8:30am

Coordinate web group for Desktop version deployment

Entai - Dave and George will fill in in Entai’s absense

12

Completed

9:00am

Update Version

George

Note: need more info on exactly what gets updated.

13

Complete

9:00 am

Quick testing in PROD. And let Xu know if issues or not. 1) Can access via Web? 2) Download? 3) Version? 4) Download Folder? 5) Others?

 

Notify the ROFs team that the database is ready.

Honglei

14

Complete

9:00

Update minimum version in WR203 parameter CD in ATTR1420 and ATTR1430 to the release version 1.35.0.0

Xu

15

Complete

8:30 am

Let TC DBA know PROD is ready for a backup and refresh Servicedesk with PROD backup

Xu

16

Complete

8:30 am

TC DBA refresh Servicedesk with PROD Copy and let us know once done.

Xu

17

Complete

9:10 am

ServiceDesk Build and version number update.

George

18

Complete

9:30am

In SD, Data set up. 1) Attributes 2) Roles/Tasks 3) User recreate, Permission scripts 4) Remove start up message 5) Unlock the system

Shu Zi, Xu

19

Complete

10:00am

SD Sanity Test and let Honglei know can start smoke testing

Xu

20

N/A

11:50am

Let Help Desk know they can start smoke test

Honglei

21

 

10:00am

Smoke testing

RSIG QA, Helpdesk, Users

22

Complete

3:00 pm

Update SD SSIS scripts to

  1. update PROD ROFS endpoint to ACC

  2. update attributes/authorization for new users Steve

Xu

23

Complete

9:00am

TC DBA refresh RSIG_TRAINING with PROD Copy

Xu and TC DBA

24

Completed

Anytime

RSIG Training Build

George

April 29th, 2023 (Saturday)

Item

Status

Time (Estimate ONLY)

What to Do

Who

Item

Status

Time (Estimate ONLY)

What to Do

Who

25

Complete

Morning

Coordinate with Citrix team. Citrix testing and let team know if testing is done. Close SMGS Ticket.

Honglei

26

 

 

Option: Consult with Manager and TL if there is any concern.

Dave, Xu

27

Complete

 

Unlock RSIG. Let team and Helpdesk know RSIG is released. Close SMGS tickets.

Xu

28

Complete

 

Inform Data warehouse Group (André Roy) for release

Xu

29

Complete

 

Inform Trevor for release

Xu

May1st, 2023 (Monday)

Item

Status

Time (Estimate ONLY)

What to Do

Who

Item

Status

Time (Estimate ONLY)

What to Do

Who

30

 

 

Close SMGS tickets.

Entai

(Dave to do this in Entai’s absence)