Release v1.3.0 - August 4, 2023 (Option 1)

 

5Sprint

Due Date

Activity

Team Member(s)

Status

5Sprint

Due Date

Activity

Team Member(s)

Status

Sprint 35

Tuesday July 18th

Release 1.3.0 active development ends

ROF team

Not Started

Sprint 36

Wednesday July 19th - Thursday July 20th

Submit SMGS ticket

Maggie

Not Started

Sprint 36

Wednesday July 19th - Thursday July 20th

ACC testing - frontend

Frontend test v1.1.0

ACC testing - backend

 

Ewa, Tarek & Jugraj

 

Not Started

Sprint 36

Wednesday July 19th - Tuesday July 25th

UAT testing

UAT v1.1.0

 

Maggie, UAT testers

Not Started

Sprint 36

Wednesday July 19th - Wednesday July 26th

Release 1.3.0 bug fixes (as necessary)

ROF team

Not Started

Sprint 36

Wednesday July 26th

Email users - ROF will be offline Friday August 4th - Monday August 7th

Maggie

Not Started

Sprint 36

Thursday August 3rd

Note: 1 week delay in prod staging after ACC testing / UAT is complete

Prod staging test

Prod staging test

 

ROF team; Cary

Not Started

Sprint 36

Friday August 4th

Note: 1 week delay in prod release after ACC testing / UAT is complete

Release to prod

ROF offline until Monday August 7th - TBD

Jugraj

Not Started

Sprint 36

Monday August 7th

ROF back online

Jugraj

Not Started

Sprint 36

Monday August 7th

Email users - ROF is back online - TBD; release notes

Maggie

Not Started

Day 1: Release Activities - Thursday August 3rd

Start Time (approx.)

Time to Complete

Activity

Team Member

Details

Status

Start Time (approx.)

Time to Complete

Activity

Team Member

Details

Status

1

8:30am

10 min

Assign QA test roles in prod:

  • Ewa - Manager

  • Maggie - RSI

Jugraj

 

Not Started

2

8:45am

15 min

Merge ACC branch with prod branch

Jugraj

 

Not Started

3

9:00am

20 min

Manually deploy from main branch to prod_staging deployment slot 

Jugraj

 

Not Started

4

9:30am - 11:30am

2 hours

Prod staging test

Cary - test Admin role

Ewa - test Manager role

Maggie - test RSI role

Jugraj - available for troubleshooting

Not Started

5

11:30am

10 min

Remove testers from prod roles

Jugraj

 

Not Started

Day 2: Release Activities - Friday August 4th

Start Time (approx.)

Time to Complete

Activity

Team Member

Details

Status

Start Time (approx.)

Time to Complete

Activity

Team Member

Details

Status

1

8:00am

10 min

swap 'prod_staging' deployment slot with 'prod'

ROF remains offline until Monday August 7th - TBD

Jugraj

 

Not Started

Day 3: Release Activities - Friday August 4th

Start Time (approx.)

Time to Complete

Activity

Team Member

Details

Status

Start Time (approx.)

Time to Complete

Activity

Team Member

Details

Status

1

8:30am

10 min

ROF back online - TDB

Jugraj

 

Not Started

Test Documents

Title

Document